October 14, 2004

It was another night of cold gray skies but the rain stopped. I got a late start but did get time to remove a raised floor area in the loft or attic space. This raised floor was to cover the extra 4" of insulation that I wanted over the office area. Since this area over the office extended into the attic area I nailed 2 X 4's on the floor, insulated it, and covered it with 1/2" plywood. I removed all of this framing and am nearly ready to start removing the rough floor boards.